COPY OF NEWTOWN, CT 2004
PLAN OF DEVELOPMENT TEXT
CONCERNING SEWERS
The following text is drawn from the 2/2004 Newtown, CT Plan
of Conservation and Development:
Public sewer service plans and policies are the responsibility
of the Town's Water Pollution Control Authority, which amended
the Water Pollution Control Plan in 1999. Public sanitary
sewer service is new to Newtown, having been completed since
the preparation of the 1993 Plan of Development.
Newtown’s
public sewer system was developed in conjunction with a municipal
sewer avoidance program. The municipal sewer system was designed
to address sewage disposal problems and the Town’s sewer
avoidance program is designed to eliminate the need to extend
the municipal sewer system to serve additional residential
areas in the future.
Newtown’s
municipal sewer system serves the central area of the Town,
including most of the Borough and Sandy Hook Center, as described
on the attached map. The system’s treatment plant was
developed jointly with the State of Connecticut and was designed
to serve Town needs, the State’s Garner Correctional
facility and the future use of the abandoned Fairfield Hills
hospital complex. The Town will most likely receive additional
access to the plant’s treatment capacity once the acquisition
of Fairfield Hills has been completed.
The
sewer system contains approximately twenty miles of piping,
four pump stations and a treatment facility located at the
end of Commerce Road with the capacity to treat 932,000 gallons
of sewage daily. Current sewage treatment at the plant averages
500,000 – 600,000 gallons per day. The system was completed
in 1997.
The
intent of the Town’s sewer avoidance policies are to
foster the maintenance of existing onsite septic systems outside
of the sewer service areas and avoid the need to extend sewer
service beyond the current limits of service to serve failed
systems.
Public sanitary sewer service is also provided within the
Route 6 corridor in the Hawleyville area of Town, extending
toward the Bethel town line. Sewer service within this area
is pumped into the City of Danbury’s municipal sewer
system and treated at the City’s Plumtrees Road treatment
facility, as per an inter-municipal agreement that provides
Newtown with the treatment capacity of up to 150,000 gallons
of sewage per day.
The
sewer service provided within the Hawleyville area pursuant
to this agreement is intended to primarily serve economic
development activities. To date, approximately 30,000 gallons
of this capacity has been allocated for two area uses.
NEWTOWN,
CT SEWER SERVICE
HISTORY (UPDATED ONLY TO 1992)
In 1963 and 1969, Pollution Abatement Reports were prepared
for Newtown by the firm of Henderson & Casey. In 1967,
the Town received an order from the Connecticut Water Resources
Commission to construct a sewage collection system in order
to provide sewer service to the central area of Newtown. Collected
sewage was proposed to be treated by a sewage treatment plant
to be located at the confluence of the Pootatuck and Housatonic
Rivers.
In 1977-1978,
the engineering firm Center for Environment and Man prepared
a sewerage report for the U.S. EPA and CT DEP entitled Tri-Town
201 Wastewater Facilities Plan for Newtown, Southbury and
Woodburv. Areas of Taunton Pond and the Newtown Borough were
found to have the greatest need for municipal sewer service.
Field surveys conducted in 1976 of on-site septic systems
within the Newtown Borough found approximately 10% of the
systems to be failing.
In 1979,
a Citizens Advisory Committee was appointed as liaison between
the consultant Center for Environment & Man and the Town.
In 1981 a Water Pollution Control Authority was appointed
by the Board of Selectmen to finalize the Town’s sewer
pollution abatement plan. In 1984, the final report by the
consultant was issued and addressed sewer issues in Newtown,
Southbury and Woodbury. The resulting sewer pollution abatement
plan for Newtown was adopted by the WPCA and had an estimated
cost of $13 million.
The mapping of soils and septic failures within Newtown had
shown chief areas for concern to be the Borough, Sandy Hook
and a south central area along Main St. These were proposed
to be the first areas to be served by municipal sewers. A
sewage treatment plant with a capacity of 1.2 MGD was to be
constructed on land donated by Fairfield Hills State Hospital,
discharging treated sewage effluent into Deep Brook, which
runs northward to the Pootatuck River.
Community
waste disposal systems using leaching fields were recommended
for parts of Shady Rest, Riverside, Pootatuck Park and Cedarhurst/Lakeview
Terrace. The most cost-effective systems were seen as individual
small grinder pumps to push effluent through small diameter
force main sewer lines to large leaching fields. In addition,
the report urged the Town to adopt a comprehensive sewer avoidance
program that would:
- prohibit
conversion of seasonal properties to year-round use.
- require septic tanks to be pumped and inspected annually.
- require the installation of low-flow water fixtures.
- require the inspection of systems which have been repaired
or replaced, one year after completion of improvements.
- test all water supply wells on a regular basis.
A 1989
sewer report was prepared by Consulting Environmental Engineers,
Inc. and focused on Newtown only. All areas within the proposed
sanitary district boundary were to be closely monitored for
sewer pollution problems. It was assumed that all areas within
the sanitary district would eventually be connected to the
sewer system. This sewer plan was rejected by voters in October
of 1989 and sent back to the WPCA for revision.
In 1990,
Consulting Environmental Engineers, Inc. prepared an Addendum
to their 1989 report. The Addendum reduced the cost of the
sewer plan to $65 million by excluding some outer areas. Under
this plan, approximately 1,200 of Newtown’s 7,000 homes
would be sewered, concentrated primarily within the Borough
area.
According
to this plan, users would pay 62% of the cost, and the remaining
38% would be paid by the Town at large. Four million dollars
for design of the sewerage system was then approved by the
Newtown Legislative Council and subsequently rejected at a
Town Meeting. As a result, the CT DEP then asked the Connecticut
Attorney General’s Office to take legal action against
Newtown for failing to correct groundwater pollution.
Also in
1990, Newtown voted $2 million for the enlargement of the
Bethel portion of a sewer line which Bethel was designing
to serve the Route 6-Stony Hill area. Newtown desired to expand
the capacity of the Bethel portion of this sewer line in order
to have the option to extend the sewer line into the Hawleyville
area and serve the land zoned for commercial/office/industrial
use along Route 6 and at the intersection of Route 25 and
1-84 at Exit 9. The Bethel portion of this sewer line has
been enlarged to permit a Newtown flow capacity of 0.4 MGD.
In 1991,
the Newtown WPCA proposed a $33.2 million sewerage plan. Under
this plan much of the Borough and Taunton Lake North neighborhoods
would be sewered and served by a $5.3 million treatment plant.
The Sandy Hook area would also be sewered and would be served
by a separate neighborhood septic system to be constructed
near Treadwell Park. See the figure entitled Town of Newtown
Proposed Sewer Service Areas.
The Town
reached an agreement with the State in 1991, establishing
a timetable for the adoption of a program to resolve its identified
sewer problems. The agreement called for the adoption of such
a program by the Spring of 1992. If a program was not adopted
by that time, the State would seek implementation of a fine
against the Town. The Town adopted a $34.3 million sewer plan
on April 7, 1992 in a town-wide referendum.
NEWTOWN
CT’S CONSIDERATION
OF SEWAGE TREATMENT OPTIONS
(UPDATED ONLY TO 1992)
In 1967, the Town received an order from the Connecticut Water
Resources Commission to construct a sewage treatment plant
to be located at the confluence of the Pootatuck and Housatonic
Rivers. This plant would have treated sewage from a proposed
sewage collection system serving the central area of Newtown.
Newtown did not implement this early sewer plan and the Housatonic
River site for a plant is no longer under consideration.
The WPCA’s
1991 scaled down $33.2 million sewerage plan recommended the
construction of a $5.3 million municipal sewage treatment
plant, with a 0.271 MGD capacity, to serve the Borough and
Taunton Lake North areas. This plan was adopted at a town
meeting in March of 1992. A subsequent town-wide referendum
in April of 1992 adopted a $34.3 million sewer plan.
The Town
is investigating the possibility of using the State owned
sewage treatment plant located on the grounds of Fairfield
Hills State Hospital to treat collected municipal sewage from
these two areas. The engineering firm of Metcalf & Eddy
prepared a report on this facility for CT DEP in March of
1992.
The report examined the possible upgrading and expansion of
this facility from its current 0.481 MGD capacity to 0.75
MGD capacity, which would be of sufficient size to accommodate
the Fairfield Hills Hospital, the State Jail and the 0.271
MGD of effluent projected to be generated by the Town’s
proposed sewer system serving the Borough and Taunton Lake
areas.
The Town
is also investigating the concept of taking over the operation
of this State treatment facility and providing treatment services
to the State hospital, the jail, and to the Town. Under such
an arrangement, it may be possible for Newtown to realize
significant savings, as the cost to upgrade and expand the
existing State treatment plant to accommodate the Town’s
sewage treatment needs may be as much as $3 million less than
the cost of the Town building a new sewage treatment plant
of its own to serve the Borough and Taunton Lake sewer service
areas.
The WPCA’s
adopted 1992 sewer plan proposed to construct a neighborhood
septic system near Treadwell Park to treat sewage collected
from the proposed sewer system serving the Sandy Hook area.
Septage from this facility would be trucked to the Danbury
sewer plant for treatment.
The ultimate
destination for the sewage collected by the sewer line serving
the Hawleyville Stony Hill areas of Newtown and Bethel is
the sewage treatment plant in Danbury. Discussions with Danbury,
to purchase a share of Danbury’s sewer plant capacity,
are continuing.
A portion
of the expanded Danbury treatment plant’s total capacity
has been set-aside by CT DEP to meet regional sewage needs.
This regional capacity has already been allocated by CT DEP
to Brookfield and New Fairfield in shares of 0.3 MGD and 0.7
MGD respectively. If these allocations stand, Newtown will
need to purchase a portion of the plant’s treatment
capacity which has been allocated by DEP to treat Danbury
sewage.
Danbury would like to be able to allocate a portion of this
additional regional capacity to Newtown for its proposed sewer
line serving the Hawleyville area. This would maintain the
integrity of Danbury’s share of the treatment plant’s
capacity and would provide fiscal relief to the City, with
Newtown paying for a portion of the construction and maintenance
costs of the CT DEP mandated additional regional capacity.
In addition
to the existing treatment plant serving the Fairfield Hills
State Hospital, Newtown businesses, housing developments,
and government facilities may have CT DEP regulated permits
to discharge wastewater directly into Newtown watercourses.
|