For a transportation
project in Brookfield to obtain a commitment of federal transportation
funds, it must first appear on the HVCEO maintained list below.
This listing also assists local officials in tracking the
progress of current improvements,
and planning and advocating for future
improvements as well.
CURRENT ROUTE 7: BYPASS
--- Conn DOT project 18-113 is the relocation of the portion
of Route 7 extending from the temporary end of the Route 7
Expressway in Brookfield, northward to the New Milford Town
Line. This new roadway segment (see
detailed pdf Conn DOT map) will
pass to the west of current two lane Route 7 in Brookfield's
"Four Corners" area.
The Route
7 Bypass will have a four lane cross section with north-south
travel lanes divided by a "Jersey" type concrete
median barrier. There will be no access (intersections or
driveways) to the new Bypass.
The south end of the Bypass will connect to the temporary
end of the Route 7 Expressway at an expanded four way interchange
with Route 202 (Federal Road). The north end of the Bypass
will reconnect to the existing Route 7 alignment, just south
of the New Milford town line, at a new signalized intersection.
North of that point existing Route 7 in New Milford will be
widened to four lanes.
Conn
DOT projections of average daily traffic for the year 2012
are revealing as to how volumes will change in central Brookfield
once the new Route 7 Bypass is in place.
Without
the Bypass, the 15,000 daily vehicles traveling north on the
Route 7 Expressway will as now all exit to combined Routes
7 and 202. But with the Route 7 Bypass in place the northbound
exit volume of 15,000 falls to 7,250, the remainder of 7,750
remaining on the new northbound Route 7 Bypass.
Just
north of the current Route 7 Expressway terminus northbound
Route 7 traffic is mixed with volumes from Route 202. The
traffic projection here for 2012 estimates this northbound
volume as 18,700 without the Bypass and 9,050 if it is built,
a drop of just more than 50%.
This
drop in volume will continue on “old” Route 7
thru the Four Corners - Route 25 intersection area. Conn DOT
anticipates that once the Bypass is built then northbound
volumes just south of the signal at Route 25 will be reduced
by 60%, and then north of Route 25 reduced by close to 70%.
Looking
at the total volume for both directions on Route 7 north of
the Four Corners, the 2012 volume without the Bypass is projected
to be 29,900. But with the diversion provided by the parallel
Bypass this falls to a much lesser 9,700.

The
new Route 7 as it will look through Brookfield. At Route 133
(yellow area and circle) Brookfield proposes to add a half
interchange with Route 7 ramps to and from the south.
Construction
began in May of 2007. The project is then expected to take
three years to complete. Contact: John Trovato (860) 594-3194.
FUTURE
ROUTE 7: POTENTIAL
NEW ROUTE 133 INTERCHANGE
—
Once the Route 7 Bypass is completed and traffic patterns
make adjustments, undertake a planning study to determine
the feasibility of a northbound exit ramp and a southbound
entrance ramp ("half interchange") from the Route
7 Expressway to Route 133. See more detailed discussion in
regional plan section entitled Route
7 North of Danbury.
FUTURE I-84: WIDENING
— Widening of I-84 from 4 to 6 lanes in conformance
with Conn DOT’s 2000 I-84 Plan. Cost estimate is part
of the $38,470,000 needed to widen I-84 between Exit 8 on
the Danbury -Bethel line thru Brookfield easterly to Exit
9 in Newtown.
CURRENT ROUTE 202: INTERSECTION
AT SILVERMINE ROAD AND ELBOW HILL ROAD
Conn DOT project 18-118 will result in the alignment of the
off-set intersections of Route 202 with Silvermine Road and
Elbow Hill Road into one four-way, signalized intersection.
This project is under construction as of April 2008. Conn
DOT Contact: Hugh Hayward (860) 594-3279.
CURRENT
ROUTE 202: IMPROVEMENTS
FROM WHITE TURKEY ROAD TO RT 133
Project No: 18-124 includes lane widening and lane continuity
to address safety concerns along this busy section of Federal
Road. Preliminary concept plans were prepared and a public
information session was held on 4/16/2002 to receive public
comments.
Additional
survey information is being obtained. Alternative concept
plans are being prepared to address identified concerns and
may be ready for public review early in 2008. The current
project cost estimate of $10,000,000 will likely be reduced
as a result of design changes being considered.
While the next set of public
review meetings will not be held until 2008 but affected individual
businesses and local interest groups can meet before then.
As of 5/2008 the project is moving ahead but is still beneath
the 30% design stage, meaning that it remains conceptual and
can be modified.

A key item on this Brookfield
project list is the addition of turning
lanes and shoulders along the Route 202 commercial area.
A new link from the signal at
Kohl’s driveway easterly to Gray’s Bridge Road
is being considered as part of the project. But extending
Huckleberry Hill Road easterly to Route 202 is no longer seen
as feasible. The state bridge over the Still River may need
to be widened in order to accommodate another lane.
The need for sidewalks was not brought up
in the first review meeting a couple of years ago, but Conn
DOT is definitely open to discussion of their inclusion. They
would need input on pedestrian needs, and options other than
building a sidewalk the full length of the project are possible.
HVCEO staff suggested that the Town share of sidewalk costs
may be waived given the new emphasis on Smart Growth and pedestrian
movement at Conn DOT.
The
contact is Conn DOT Project Engineer Scott Bushee at 860-594-2079.
FUTURE
ROUTE 202: IMPROVEMENTS IN THE
ROUTES 202 AND 25 INTERSECTION AREA TO
FACILITATE DEVELOPMENT OF THE BROOKFIELD VILLAGE
MAke changes to Route 202 (as Route 7 in Brookfield
Center will be known after the Route 7 Bypass is consturcted0
in coordination with the the construction of the Brookfield
Village mixed use development.

Excerpt from Brookfield Village
Center
Plan showing major changes to Route 7
FUTURE
PEDESTRIAN
IMPROVEMENTS
IN BROOKFIELD:
The Brookfield Plan of Conservation and Development
proposes the development of “A walkable village type
development pattern in the Four Corners area,” including
the establishment of “a network of pedestrian sidewalks”
there, and also “pedestrian friendly streetscape”
and “interconnected parking areas and pedestrian walkways.”
The Brookfield
Plan is also admirable in that it contains a full page and
definitive townwide “Sidewalk Plan” for the municipality,
using color to denote primary and secondary sidewalk areas
and recommended future connections. The main Federal Road
commercial area is identified as a primary sidewalk area.
According
to the “Sidewalks” section of the Brookfield Plan
“The lack of sidewalks and the low-density pattern of
development in Brookfield limits pedestrian circulation. Existing
pedestrian facilities, such as sidewalks and crosswalks, are
basically located in some of the main retail areas Route 202
and the Four Corners area.”
FUTURE
TRANSIT IMPROVEMENTS IN BROOKFIELD:
— Advance Brookfield
bus and rail transit projects when funding permits.
—
Construct Still River Multi-Use Trail from Town Hall north
to Four Corners. The 2003 cost estimate was $550,000.
This project
received the top regional priority for federal Enhancement
program funding. In December of 2005 Conn DOT announced that
a grant of $400,000 towards the total cost had been awarded
for this project.
|