1.
NEWTOWN'S NEAR FUTURE
TRAFFIC IMPROVEMENTS:
ROUTE 6 SAFETY IMPROVEMENTS
FROM RAILROAD OVERPASS EAST TO I-84 EXIT 10
Conn DOT Project 0096-0192 calls for Edmond Road to be realigned
to meet Commerce Road on Route 6 (Church Hill Road). And Newtown's
Town Plan calls for this project to further coordinate with
a potential new access road from Church Hill Road easterly
to Wasserman Way via an extension of Commerce Road.

An
important improvement in Newtown is the
reduction of accident rates on Route 6 from Commerce
Road, shown at right, easterly to I-84 Exit 10.
Conn
DOT has identified this busy segment of Newtown's Route 6
as a high frequency accident location. Recent
federal transportation legislation contained two Congressional
Earmarks to fund the implementation of the project. One totals
$1,600,000 to fund the Edmond Road relocation and the second
totals $2,000,000 to fund safety improvements on adjacent
Route 6.
For this
project to proceed it was necessary for Edmond Road to first
become a public road. This was accomplished by the Town in
January of 2006.

Route
6 accident reduction will be accomplished in part by the relocation
of
unsignalized Edmond Road (light green at right) westerly to
align as a new road
(with yellow center line) with Route 6 across from the intersection
with Commerce
Drive, coupled with incorporation of a median divider (green).
As
shown above, a newly installed variable width median divider
will be constructed along Route 6 from Commerce Road to I-84
Exit 10. The median includes a "vehicle turning gap"
break near the existing intersection with Edmond Road.
The southern end of Edmond Road will be shifted west and signalized
at Route 6. The existing southern end of Edmond Road will
be removed.
This project
is on the HVCEO 2010-2013 Transportation Improvement Program
(TIP).
The contact person at Conn DOT is Hugh Hayward at 860-594-3279
and hugh.hayward@ct.gov.
ROUTE 25 INTERSECTION
IMPROVEMENT AT PECKS LANE NORTH
This project was submitted by Newtown and reviewed by the
Conn DOT Project Development Unit. The preliminary review
was completed in September of 2006 yielding a cost estimate
of $1,890,000, with the improvement concept involving separation
of Prospect Drive from Pecks Lane.
The
project had its public information meeting in Newtown on 12/19/2007
and has been approved by Conn DOT for its engineering phase.
But as of 12/2009 Conn DOT is waiting for engineering funds
to become available thru the FHWA STP-O funding source before
proceeding. As such, the Department has not started preliminary
design on this project yet. The Department anticipates the
funds may become available in 2011.
The
Conn DOT Project Manager is Timothy Gaffey at 860.594.3287,
timothy.gaffey @ct.gov, and the Project Engineer is Susan
Libatique, 860.594.3179, susan.libatique@ct.gov.
COMPLETE I-84 ENVIRONMENTAL IMPACT STATEMENT
Cooperate with adjacent municipalities towards the
completion of the on-going Conn DOT I-84
Environmental Impact Statement process. Newtown
officials will need to monitor this process to insure that
environmental impacts from the proposed widening are acceptable
to Newtown.

COMPLETE I-84 CLOSURE
TRAFFIC DIVERSION PLAN
This emergency management action plan will be completed
by DEMHS 5, COGCNV and HVCEO during 2010.

Eighteen
hour I-84 expressway closure
requiring traffic diversion thru Newtown.
State Police, Conn DOT and Newtown officials will then rely
upon one coordinated set of diversion instructions for managing
increased traffic due to the temporary closing of expressway
lanes and exits during an I-84 emergency.
CONSIDER
IMPACTS
UPON
NEWTOWN OF I-84 TOLLING PROPOSALS
The return of tolls to Connecticut's expressways is seriously
proposed in Hartford. If tolls are added to I-84 in or near
Newtown in order to raise road improvement funds, then the
Town would be heavily impacted by the diversion of traffic.
These impacts have been identified in HVCEO's research
report #141. That report may be utilized by officials
and citizens during any future toll plaza planning hearings.

STATE
ROADWAY DRIVEWAY
AND CURB CUT MANAGEMENT PLANS
These curb cut plans consist of a series of adjacent
maps showing all properties, all driveways, and the recommended
reorganization of driveways as properties develop or redevelop.
Implementation
comes thru use of the maps by local planning and zoning commissions
and by Conn DOT administrators for state roads when conditions
of approval are set.

Legend from Newtown's
2010
Driveway and Curb Cut Management Plan
A
text supplements the maps, giving traffic engineering advice
for each property where there is a recommendation for a change
of driveway. These mapped driveway standards appear in the
zoning regulations of Bethel, Brookfield, New Milford, Newtown,
Redding and Ridgefield, all prepared by HVCEO.
The Newtown
Curb Plan has recently been brought up to date. See the Newtown
2010 Access Management Plan. See also a regional
map of completed plans.
2.
NEWTOWN'S LONGER
RANGE TRAFFIC IMPROVEMENTS:
FUTURE ROUTE 6 IN HAWLEYVILLE:
In accordance with HVCEO's 1997 Exit
9 Hawleyville Transportation Study, increase
the number of lanes and add turning lanes on Route 6 in the
Hawleyville Area as adjacent development warrants.
FUTURE ROUTE 25 IMPROVEMENTS AT EXIT 9
In accordance with the HVCEO's 1997 Exit
9 Hawleyville Transportation Study, provide progressive
signalization, coupled with widening of Route 25 to four lanes
with turning lanes in the vicinity of Exit 9.

Route
25 looking north just past I-84
"before" and "after" views of widening
proposed
by the Exit
9 Hawleyville Transportation Study.
FUTURE ROUTE 25 INTERSECTION
IMPROVEMENT AT COLD SPRING ROAD
Improvements to the intersection of Route 25 at
Cold Spring Road, including a traffic signal. This project
was submitted by Newtown to Conn DOT in July of 2004 as
the fourth of four priorities and is inactive due to lack
of federal and state funds.
FUTURE ROUTE 34 INTERSECTION
IMPROVEMENT WITH POLE BRIDGE ROAD
This project was submitted by Newtown to Conn DOT
in July of 2004 for review by the Conn DOT Project Development
Unit to assess potential for federal funding. Conn DOT informed
Town staff in September of 2006 that the cost to benefit ration
for this potential project appeared low in comparison to other
needs such as the northern intersection of Route 25 with Peck's
Lane.
FUTURE
I-84 EXIT 11 REDESIGN
Conn DOT project 34-308 calls for rebuilding I-84 Exit 11
into a four way diamond interchange with an access road that
will intersect with Route 34 across from Wasserman Way. This
project evolved from the Conn DOT 2000 I-84 Improvement Plan.
The reconfiguration of I-84 Exit 11 is intended to improve
roadway safety and traffic flow during peak periods.
The elaborate
high speed Exit 11 was constructed in the early 1970s in preparation
for a linkage between I-84 and the planned Route 25 Expressway.
But the Route 25 Expressway plan was abandoned, leaving Exit
11 as an overbuilt set of ramps, as shown below:

See
full details of Conn DOT 2007
Plan for Exit 11.
The existing J ramp configuration, intended to be temporary
in the 1970s plan, will be removed and on and off ramps will
be reconstructed to intersect directly with Route 34 (historical
note: as they did originally when I-84 first opened).
Conn DOT held a public information meeting on this project
in June of 2007. As of 12/2009 the project design is at about
the 80% completion level, but the project will not advance
into construction as funding levels are not sufficient.
This
vicinity was cited by a 2001 Conn DOT study as a possible
new I-84 truck stop and rest area location. However it was
not included in the final 2007 Conn DOT Statewide Rest Area
Study.
FUTURE
I-84 MAJOR WIDENING
AND INTERCHANGES 9 AND 10 REDESIGN
Rebuild I-84 Exit 9 (see
future Exit 9 map) and Exit 10 (see
future Exit 10 map) in accordance with the Conn
DOT 2000 I-84 Plan.
FUTURE ROUTE 302 INTERSECTION
IMPROVEMENT AT HATTERTOWN ROAD
This project was submitted by Newtown to Conn DOT
in July of 2004 as the third of four priorities and was reviewed
by the Conn DOT Project Development Unit to assess potential
for federal funding. But
the cost to benefit ration for this potential project appeared
low in comparison to other municipal needs such as the northern
intersection of Route 25 with Peck's Lane.
FUTURE
SANDY HOOK CENTER IMPROVEMENT:
Complete the Sandy Hook Center streetscaping plan,
including possible geometric revisions to the intersection
of Glen Road with Washington Street and Riverside Drive.
Streetscape on the western side of the intersection below
was completed in 2006, while that on the eastern and northern
segments remains to be completed. The
enhancement of existing sidewalks and the construction of
new ones in this area enhances overall pedestrian circulation
and safety.

Partially completed beautification
and sidewalk plan for Sandy Hook Center.
FUTURE
NEW LOCAL ROAD FROM
ROUTE 6 TO WASSERMAN WAY (ROUTE 860)
The
Queen
Street Area Traffic Improvement Plan was completed
by HVCEO in August of 2006. It included traffic projections
for a nearby proposed link from Commerce Road southeasterly
to Wasserman Way which may divert some Queen Street traffic.Both
the 1992 and 2004 Newtown Plans of Conservation and Development
recommended consideration of this new roadway.
This proposed
connecting roadway would link Church Hill Road (Route 6) at
its western terminus with Wasserman Way (Route 860) at the
eastern terminus. This new collector road will connect with
Route 6 at Commerce Road directly across from where an upcoming
major federal investment is to realign Edmond Road with Route
6 at Commerce Road. The new roadway will provide a link between
I-84 Exits 10 and 11.
According
to a 2006 HVCEO traffic study the addition of this important
link would help alleviate traffic pressures on the nearby
central areas of Newtown.
From a
broader geographic perspective and over time, the introduction
of this new collector roadway could increase travel choices
and better distribute both local and thru traffic in central
Newtown. It is also to provide access to major economic development
initiatives.
But the environmental impacts of this proposal, including
its affect upon Deep Brook, will need careful scrutiny.
3.
NEWTOWN'S OTHER
TRANSPORTATION IMPROVEMENTS:
FUTURE
LOCAL PEDESTRIAN IMPROVEMENTS:
Continue to implement the 2003 Queen
Street Pedestrian Safety Plan.

That
2003 report summarizes pedestrian improvements for three distinct
segments of the Queen Street Corridor between Route 6 (Church
Hill Road) and Glover Avenue in Newtown;
1) Intersection of Route 6 and Queen Street,
2) Queen Street from Route 6 southerly to Glover Avenue, and
3) Intersection of Queen Street and Glover Avenue.
Facilitate
pedestrial access to the Monroe regional trail during Batchelder
Property site redevelopment.
TOWN
OF NEWTOWN BRIDGES WITH SPANS GREATER
THAN 20 FEET PERIODICALLY INSPECTED BY CONN DOT
Cooperate with Conn DOT on proper maintenance of such bridges
on Pond Brook Road, Currituck Road, Georges Hill Road, Hanover
Road, Walnut Tree Hill Road, Covered Bridge Road and Old Hawleyville
Road.
4.
NEWTOWN'S SHORT RANGE
BUS SERVICE IMPROVEMENTS:
The
HVCEO 2010-2013 Transportation Improvement Program (TIP)
indicates federal funds are reserved
for modernizing the fleet of HART
vehicles serving Newtown's elderly and disabled.
5.
NEWTOWN'S LONGER RANGE
BUS SERVICE IMPROVEMENTS:
(Excerpts
from 2010 Bus Service Improvement Plan)
NEWTOWN
FIXED ROUTE HART BUS
Create a new
Danbury - Bridgeport link serving Newtown via
route 6 and 25. The Bridgeport to Danbury service would provide
trips for people working and living on either end of the route
and provide local service to points along the corridor at
retail, office and manufacturing locations. The service could
also act as a shuttle from the park and ride lot at the junction
with Route 111 in Trumbull to the MTA Metro-North Railroad’s
New Haven Line station in Bridgeport.
Current proposals are for a three bus service during the weekday
peak travel period. The service would be operated jointly
by the Greater Bridgeport Transit Authority and the HART system.
Bus fares would be integrated with the two systems.
Make enhancements to the existing Peter Pan bus schedule that
would provide three additional a.m. round trips and four additional
p.m. round trips between Danbury and Waterbury Monday through
Friday. An additional route stop in the exit 10 area of Newtown
(the location of an historic intercity bus stop) would be
added on these trips. This location would also serve as a
transfer point to the
planned Danbury-Bridgeport service.
As part of the resumption of passenger service to New Milford,
a second Danbury station stop near the Brookfield line is
planned. Locations for this stop are being evaluated as part
of the current DOT study, with suggested locations within
the Berkshire Industrial park, or opposite the existing White
Turkey park and ride lot.
Rail user demographics suggest a peak period rail feeder shuttle
from the exit 10 or 11 of I-84 areas of Newtown to this new
station may be an appropriate option.

NEWTOWN SWEETHART BUS
For the long term, reduce costs by establishing a new regional
SweetHART service that would serve Newtown and nearby towns
in a more efficient manner than the town by town approach
at present.
•
To the extent feasible facilitate Newtown's
commuter travel patterns by bus services.
|