1.
INTRODUCTION 2.
DOWNTOWN 3.
GROVE ST 4.
BOARDMAN RD
5. E-W CONNECTOR 6.
RIVER BRIDGES 7.
TRAFFIC IMPROVEMENT
INTRODUCTION
Should there be an additional crossing of the Housatonic River
in New Milford, to better link the east and west sides of
this geographically very large and growing Town?
This key question has been raised many times in the past.
An important local and regional transportation planning issue,
the question remains with us today.
This section
of the Central New Milford Traffic Issues report explores
that question, but does not provide a definitive recommendation.
Rather, it summarizes past thinking on new bridge proposals
in an effort to both speed the day a decision is made and
improve the quality of that decision.
There are three bridge crossings of the Housatonic River in
Central New Milford, the Marsh Bridge on the Grove Street
Corridor to the south, the central crossing near Downtown
provided by Veterans Bridge carrying combined Routes 67 and
202, and to the north the Boardman Bridge on Boardman Road.
All three link Route 7, which remains on the west side of
the Housatonic in this part of the Town, with the east side
of the community.
POLICY AGAINST ADDING LANES
On
VETERANS MEMORIAL BRIDGE
Of the three bridge crossings, Veterans Bridge is the central
artery and by far the most heavily utilized. It was opened
to traffic in 1954 as a replacement to an earlier span. The
roadway cross-section on the bridge is limited by the bridge
design to two lanes.
As local
residents know, traffic using the Veterans Bridge has a particularly
strong relationship with Route 7 to the south. Conn DOT data
shows that in the morning peak hour, for westbound Route 67
traffic crossing Veterans Bridge to approach the intersection
with Route 7, over 75% turns south onto Route 7. The reverse
is the case for the afternoon traffic peak.
In 1995
this major span was due for major maintenance. In an effort
to examine all alternatives, Conn DOT presented a plan to
the municipality to construct a new bridge with a four lane
cross section, immediately south the existing bridge, after
which the aging Veterans Bridge would be removed. Rehabilitation
of the existing two lane bridge was also an option.
Local reaction was strongly in favor or rehabilitation of
the existing bridge. While the value of more capacity by adding
two additional thru lanes was recognized by citizens at the
hearing, it was felt that the presence of a wider cross section
on Veterans Bridge could lead to pressure to widen the adjacent
section of Bridge Street to the east. This in turn would risk
marring the historic character of Bridge Street and the adjacent
Downtown.
Also, there was considerable attachment to the
informal landmark status of the 1954 Veterans
Bridge design, with its high arching framework, entryway function
and familiarity to drivers beyond New Milford.

Conn DOT accepted these viewpoints. The option for a wider
replacement bridge was withdrawn, and the substantial federal
funds available for either option were programmed for the
rehabilitation option.
This was an important traffic capacity decision. To the extent
that more "traffic carrying capacity" for New Milford
across the Housatonic River is needed, the focus after 1995
necessarily shifted away from Veterans Bridge and towards
other locations.
NEW BRIDGE TO LINK
ROUTE
7 WITH BENNITT STREET
Proceeding
about one third mile to the north, a now venerable concept
for an additional bridge would link Bennett Street, running
east-west at the north end of Downtown New Milford Green,
westerly across the Housatonic River to Route 7. This would
be a parallel bridge to Veterans Bridge on Bridge Street,
as noted about one third of a mile to the south.

Excerpt
from the 1959 New Milford Plan of Development where the proposed
Bennitt Street Bridge connection is the northern of two crossings
shown
above, southern crossing is existing Bridge Street.
Study
of 1968. Conn DOT made an analysis of this potential
improvement back in 1968. Ending at Bennitt Street was seen
as a possible terminus to the Route 7 Expressway.
The Conn
DOT study stated that “Another alternate river crossing,
taken under study, was based upon the 1959 New Milford plan
of development which recommended a new bridge northerly of
the existing Bridge Street structure, connecting on the east
side of the river into Bennitt Street. Such a connection would
provide additional service to New Milford Center and a connection
to existing Route 202 via Elm Street. “
But the
traffic concept did not receive a favorable review; “However,
to accommodate anticipated traffic, it would have been necessary
to widen Bennett Street and Elm Street, resulting in a high
impact on adjoining developed properties.
To attain acceptable grades for roadway, the reconstruction
of the Railroad Street-Bennett Street intersection would also
have been necessary, increasing the displacement of commercial
and residential properties."
Although
officials in New Milford had considered this river crossing
previously as a part of the 1968, New Milford Plan of Development,
in 1968 they objected to such a crossing as a part of the
State highway system, mainly because of the high displacement
of properties.
It was pointed out that the connection from the west side
of the river to Bennitt Street would add considerably more
traffic to Elm Street which has a steep grade and is fronted
by two churches, a school and the New Milford Hospital, meaning
that any proposal for the widening of Elm Street would be
very strongly objected to locally.
The 1968
report concluded; “Also, traffic from Route 202 would
be using Elm Street to reach the expressway, and anticipated
high traffic volumes in the area of the hospital and the school
were not considered desirable, because of the detrimental
effect of traffic operations and pedestrian safety, and the
problem of possible additional traffic noise.
Furthermore,
any future extension of the expressway from the Bennitt Street
connection to the north seemed totally impractical, because
of a heavy area impact and difficult topography. Therefore,
this alternate was eliminated from further study.”
Study
of Early 1970's. But then a few years later, a new
bridge to Bennett Street was included in a seventies era Conn
DOT Route 7 Expressway construction alternative as a feeder/distributor
to the proposed Expressway, which had its own new crossing
to the north to reach the Eastern Segment of the East-West
Connector. This was a "two new bridges" option.
But it did not survive further review.
Study
of a potential crossing at Bennett Street then remained dormant
for many years. This is due largely to the fact that between
1972 and 1991 New Milford was expecting a new and very high
capacity Housatonic River bridge crossing as part of the Route
7 Expressway construction plan. That nearby proposal took
the pressure off of the Bennett Street Bridge idea.

Bennitt Street looking west towards Housatonic
River
Study of 1998. The concept was revived by
the Town in the late 1990's. In 1998 New Milford requested
that HVCEO undertake a traffic study to examine the feasibility
of constructing a new Housatonic River crossing from Route
7 to Bennett Street. The resultant study become HVCEO Bulletin
#96 completed in 1998.
As with
past efforts this study noted that the intent of such a new
crossing would be to relieve traffic in the Downtown and especially
on the Bridge Street section of Route 202. It was understood
from the outset of the analysis that a new parallel bridge
would not result in any traffic being removed from New Milford’s
roadways. Rather, that there might be some beneficial shifts
and redistribution of traffic within the Downtown Area.
The theoretical
second river span evaluated would cross the Housatonic easterly
from Route 7 north of Bridge Street, passing over Youngs Field
Road and the railroad tracks, to terminate at the Railroad
Street and Bennitt Street intersection. This was identical
to the 1959 Town Plan concept for such a parallel linkage.
The crossing
would have an overall length of 1920 feet, consisting of about
800 feet over the flood plain on the west side of the Housatonic,
400 feet over the River itself and 720 feet to the east linking
up with Bennitt Street. For comparison, the existing steel
arch bridge on Bridge Street is built on abutments with a
shorter span of 350 feet.

Visualizations
from 1998 study of proposed Bennitt Street Bridge.

The width
of the proposed new Bennitt Street Bridge would be 24 feet.
It would carry two lanes of traffic, with five foot side sidewalks
provided on each side. A 23 foot clearance over the railroad
tracks was built into the design.
This late
nineties "fresh look" at the old idea found that
the greatest impact of the proposed bridge would be the creation
of a new arterial route and increased traffic along Bennitt
Street and Elm Street. Also, that due to the current relatively
low volumes there, additional traffic would be perceived as
a disadvantage.
On the
positive side, the study did find that the overall level of
traffic service at the Route 202 and Railroad Street intersection
would improve slightly, along with some traffic reductions
on both Railroad Avenue and Main Street.
But overall, the study concluded that while Bridge Street
(combined Routes 67&202) volumes would be somewhat reduced,
due to the existing high volumes of traffic there, unfortunately
the reduction would not result in a noticeable improvement.
The study
projected that the morning peak hour traffic use of the new
Bennitt Street Bridge span would be 262 vehicles, all diverted
from Bridge Street. With the proposed new bridge costing at
least ten million dollars, cost benefit for this limited magnitude
of traffic diversion was not seen by the report as strongly
favorable.
ROUTE 7 EXPRESSWAY AS
NEW CROSSING OF RIVER
As noted above, from 1972 to 1991 a fourth river crossing
in Central New Milford was part of the official Conn DOT traffic
upgrade plan for the Town. This was to be in the form of a
the new Route 7 Expressway, to cross the Housatonic River
north of the Downtown.

Conn
DOT's Route 7 Expressway Housatonic River
crossing plan of 1972- 1991, with dashed line showing two
routing
options for the proposed Expressway to approach the bridge.
The 1959 Town Plan saw growth and congestion coming and concluded
that “A new bridge is therefore necessary and should
be built sometime within the next 5 to 10 year period when
traffic is expected to experience a definite bottleneck at
the existing bridge.”
Evidence
has already been provided that Conn DOT worked creatively
with alternatives for this idea. By 1962 a Conn DOT Route
7 planning report had proposed new Housatonic River crossings.
But all were south of Bridge Street, touching down near the
intersection of West Street and South Avenue, to then proceed
north to end at the intersection of Routes 67 and 202. These
were not accepted and all proposals for new crossing have
been north of Bridge Street since that time.
A 1968
Conn DOT traffic study noted that “The third alternate
river crossing would bypass the center of New Milford and
continue to the north along the Aspetuck River Valley. The
expressway would terminate at a proposed East
- West Connector Road between existing Route 202 on the
east and Aspetuck Ridge Road on the west."
The 1968
Conn DOT report concludes; “Although this alternate
would bypass the center of the Town, it still would provided
satisfactory service to this area, because the Bridge Street
crossing would be relieved by the diversion of Route 202 traffic,
and the traffic flow through the existing Route 7- Bridge
Street intersection would be further reduced by the interchange
northerly of this intersection which would allow direct service
to existing Route 7 north.
Therefore, the northerly river crossing was considered the
favorable location both by the Highway Department as well
as by New Milford officials.”
At major
public hearings in New Milford in 1968 and 1972, Conn DOT
recommended that at the terminus of the Route 7 Expressway,
a Route 202 Connector from Aspetuck Ridge Road easterly to
Route 202, be an integral part of the Route 7 Expressway plan.
This then remained the consistent Conn DOT plan for almost
twenty years, until it was dropped in 1991.
What
happened was that the planning for the Expressway, and the
new Housatonic River crossing we are discussing here, continued
for so long that much residential development appeared in
the path of the proposed roadway. To proceed would have meant
massive relocations. Elected officials in 1991 reluctantly
agreed with Conn DOT that the potential disruption from Expressway
construction was now too great to proceed.
The current
policy for Route 7 improvement in New Milford was announced
by Conn DOT on 11/26/1991 and supported by local officials.
It stated that “following extensive public discussion
and study, state and local officials have agreed on a modified
plan for improving highway travel in the Route 7 corridor
between Brookfield and New Milford ...."
Continuing
"as well as focusing upon the upgrading of the existing
two lane roadway, this plan was also to eliminate from
consideration the New Milford bypass” (italics
added). This meant the new bridge over the Housatonic
River as well as and state construction of the 1.1 mile
Eastern Segment of the East - West Connector.
6E.
PROPOSED BRIDGE CROSSING
FROM ROUTE 7 TO BOARDMAN ROAD
Would the addition of an additional crossing of the Housatonic
River, serve enough traffic to have an acceptable benefit
to cost ratio? This
question remains to be explored before the circulation plan
for Central New Milford can be finalized.
It is
remembered locally that a location on the Housatonic's east
bank on Housatonic Avenue several hundred feet west of the
West Aspetuck River is the point where the Route 7 Expressway
was originally planned to pass northward after crossing the
River.
A similar new crossing point, perhaps just west of this location,
to align directly north - south with north - south Aspetuck
Ridge Road, is has in recent years been raised as a potential
bridge crossing option.
This access
would nicely serve the proposed Century Enterprise Center.
However it would duplicate to some extent the roadway investment
planned to reach that Center via the Western Segment of the
East - West Connector and Boardman Road.
1.
INTRODUCTION 2.
DOWNTOWN 3.
GROVE ST 4.
BOARDMAN RD
5. E-W CONNECTOR 6.
RIVER BRIDGES 7.
TRAFFIC IMPROVEMENT
|