3A. ROUTE 7 IN DANBURY,
RIDGEFIELD AND REDDING, CT
INTRODUCTION
Route
7 from Danbury to Norwalk is classified as part of the top
level National Highway System. It is also a principal arterial
roadway and is the Greater Danbury Region’s main link
to the south. On a grander scale it is also the primary north-south
corridor for the western edge of New England.
The basic
alignment and cross section in our area dates from 1928. Over
the years, many spot improvements to the existing road have
been made.
More significantly, a new Route 7 Expressway parallel to the
old road was advocated by Conn DOT and HVCEO for many years.
Only short sections of the parallel expressway in Danbury
and Norwalk were ever completed.
In historical
perspective, the Connecticut General Assembly first authorized
expressway planning in this corridor IN 1957. Then Conn DOT
approved an expressway location in 1962.
Studies continued into the mid-1970's, when a federal environmental
impact statement was issued. This was challenged, first causing
years of delay, then indefinite postponement of construction.
A map of the proposed
Route 7 Expressway concept will be of
interest.
This major
new road would have entered Ridgefield from Wilton to the
west of the present Route 7. Route 102 runs generally east-west
here and a full expressway interchange with Route 102 was
planned.
Continuing northeast, the Expressway would have crossed the
existing Route 7, briefly entered Redding, then turned north
by northwest to follow the Ridgefield-Redding border, re-entering
Ridgefield briefly and then entering Redding again.
Upon passing
into Danbury from Redding, another interchange was to link
the Expressway to existing Route 7 in Ridgefield. The new
road was then to continue along the east side of existing
Route 7 to meet the existing Route 7 Expressway cross section
at Wooster Heights Road in Danbury.
Due to
funding constraints, by 1992 completion of the proposed expressway
was under reconsideration by Conn DOT. A Conn DOT policy statement
released in early 1993 stated that the expressway would still
be built, but would be delayed at least 10 years. The exception
was a small segment linking northern Norwalk to southern Wilton.
There are at present no plans at Conn DOT to revive the Route
7 Expressway construction proposal.
ROUTE 7 EXPRESSWAY POLICY
HVCEO was for many years an advocate of Route 7 Expressway
construction. However, after a policy review in 1995, HVCEO
no longer supported the construction of the proposed Route
7 Expressway in Danbury, Ridgefield and Redding.
This 1995 position was taken due to the repeated delays in
the construction of the proposed Expressway and the concurrent
invalidation of the Environmental Impact Statement justifying
the project, as well as the lack of safety and capacity improvements
on the existing Route 7 roadway, which HVCEO wished to speed.

This change
in policy was intended to fully focus all available funding
on the immediate improvements required to address safety and
capacity constraints on existing Route 7. Since under federal
law Conn DOT cannot proceed without regional approval, the
HVCEO policy is more than advisory as far as the Expressway
is concerned.
The 2001
Regional Transportation Plan added some explanatory as to
the reasons the Council no longer supported construction.
This referred to the many controversial impacts suggested
from such construction. These are given more depth by this
2004 Plan update to include:
1. Negative impact to the adjacent quality of life, both residential
and natural environment.
2. Inducing
sprawl development along the corridor and to the north, which
violates the "Smart
Growth" planning concepts in the 1997 HVCEO
Regional Plan.
3. The
Housatonic Valley Region being forced to accept housing development
pressure not wanted in the South
Western Planning Region, a problem that is more
and more in evidence by our one sided commuting patterns (much
AM southbound, little AM northbound).
4.
The inability of coastal Interstate
95, already over capacity, to absorb a newly
concentrated and expanded AM peak period traffic flow that
would enter southbound from the new Route 7 Expressway. Absorption
of our traffic onto I-95 may have been possible 25 years ago,
but is clearly problematic today.
For some
detail on this key point, consider that the 1978 Route 7 Environmental
Impact Statement projected that, taking as a specific point
of reference the cross section of the proposed Expressway
just north of the intersection of Routes 7 and 35 in Ridgefield,
that there would be about a 33% increase in total travel in
the corridor here if the Expressway were built.
A 1981
HVCEO summary of the 1978 EIS records "This increase
will be due to traffic that is diverted from existing streets
in the corridor because of the ease of travel and time savings
due to the new facility, and a rerouting of existing shopping,
business and other trips to alternate destinations due to
a shift in the relative ease of travel."
While
pro-expressway groups might well discount point one above
as "just the standard local reaction of the NIMBY (Not
in My Back Yard) syndrome", points two thru four are
systemic issues that they need to address in their arguments.
For interesting web sites that contrast with the HVCEO Route
7 perspective, visit the Route
7 Coalition and also the Committee
for the Extension of Route 7, two pro-expressway
sites.
For an anti-expressway opinion see the Road
to Ruin site. Also of interest is an independently
produced history
of planning for and upgrading of Route 7.
TOLL
ROAD FINANCING OPTION
This informational section is included as inquiries
about toll options are still received regarding Route 7 financing.
The data source is old, but all that is available.
In 1981 Conn DOT released a study on the feasibility of constructing
the proposed Route 7 Expressway between Norwalk and Danbury
as a toll road. The basic conclusion was that inflationary
construction costs, coupled with high interest rates, made
the financing of a new Route 7 by toll revenues highly questionable.
The cost
of the priority portion of Route 7 in Norwalk was seen as
comparatively high because of the complex Merritt Parkway
interchange. And the volume of traffic through a toll station
here would be low, due to convenient bypasses, thereby yielding
toll revenues that only covered 9% to 14% of the annual debt
payment for construction costs.
For the
priority portion of new Route 7 in Danbury (the Danbury to
Ridgefield section) existing Route 7 would be cut off in the
Wooster Mountain area (revised in a later expressway plan)
and there are no other roads which could function as efficient
bypasses. The resulting high traffic volumes through the toll
station here were projected to cover a more positive 55% to
70% of the annual debt payment.
The conclusion
of Conn DOT’s 1981 report was that none of the toll
concepts investigated would fully finance the construction
of Route 7 and that in most cases the share of funds provided
by the tolls would be comparatively low. As noted, the only
exception would be the Danbury portion where the net toll
revenues could cover 55 to 70% of the annual debt payment
over a thirty year period.
ACTIVITES
TO IMPROVE EXISTING ROUTE 7
Up
until December of 1999 Conn DOT remained committed to completion
of a small segment of the Route 7 Expressway from its current
northern terminus at Grist Mill Road in Norwalk to a new northern
terminus at Route 33 in southern Wilton. But Governor Rowland
announced in December of 1999 that, due to local opposition,
widening of the existing Route 7 northward to Route 33 would
replace the proposed parallel Route 7 Expressway extension
plan.
Thus the Route 7 Expressway now appears completely abandoned
by transportation planning agencies.
This said,
attention turns to better management of the existing roadway.
For the remainder of the corridor northward to Danbury, Conn
DOT is planning widening for the next segment in Wilton, followed
by the retention of the two lane cross section in northern
Wilton, Redding and Ridgefield south of the Route 7 intersection
with Route 35. Then the road will be widened to four lanes
from northeastern Ridgefield northerly to near I-84 in Danbury.
The widening
of Route 7 from 2 to 4 lanes from one half mile north of Route
35 in Ridgefield (south of which the cross section has already
been widened to 4 lanes to Route 35) northerly to just south
of Wooster Heights Road in Danbury (where the current expressway
portion ends), is scheduled to begin
construction soon as Conn DOT Projects 34-315 and 34-260.
It should
also be noted that HVCEO completed a driveway and curb cut
management plan for Route 7 in Danbury, Redding and Ridgefield
in 1996. The Redding and Ridgefield portions of the plan were
thereafter incorporated into the zoning regulations of those
communities.
ROUTE
7 WITHIN MUNICIPAL PLANS
Redding Plan of 1998: The Redding Plan states that
"unlike local town roads, where the goal is to minimize
traffic impacts in order to support preservation of the town's
essential characteristics, the traffic capacity of existing
Route 7 should be maximized to allow the road to absorb local
and connector traffic and prevent overflow on to secondary
roads such as Routes 107 and 53."
Continuing, "The Redding Planning Commission thus strongly
supports major widening and capacity improvements on existing
Route 7 and 25, the principal north-south arteries immediately
west and east of the Town and continues to recommend that
plans for 'Super 7' be abandoned."
Ridgefield
Plan of 1999: The Ridgefield Town Plan is silent
on the issue of the Route 7 Expressway.
Danbury
Plan of 2002: There is no support for the proposed
Route 7 Expressway in the Danbury Plan. The Plan constrains
Route 7 changes to "Support plans to widen U.S. Route
7 south to Ridgefield and to undertake other planned intersection
and geometric improvements."
3B.
ROUTE 7 IN DANBURY,
BROOKFIELD AND NEW MILFORD, CT
INTRODUCTION
For decades a Route 7 Expressway had been planned as a replacement
for the Danbury to New Milford portion of the 2 lane road,
and parts of that upgrading in Danbury and Brookfield were
completed. The current Conn DOT and HVCEO plan calls for an
expressway bypass to continue on to the Brookfield-New Milford
Town Line, followed by widening of existing Route 7 northerly
to central New Milford. (As of 11/2003 part of this improvement
is under construction).
From I-84
in Danbury northward to Route 202 in Brookfield, the Route
7 designation was transferred in 1977 from the historic two
lane roadway to a parallel Route 7 Expressway newly completed
that year.
A Conn
DOT Route 7 Expressway policy for the Brookfield-New Milford
corridor was released in 1990 in the form of a Conn DOT Environmental
Impact Evaluation (EIE). The Conn DOT 1990 EIE favored expressway
construction rather than lesser improvements.
However, due in no small part to strong opposition from potentially
impacted property owners, Conn DOT announced in November of
1991 that the finalized EIE would "postpone further evaluation
of an expressway in the corridor until such time as interim
improvements fail to provide adequate service and direction
is mandated by the Legislature."
CURRENT
UPGRADING PLAN
The current corridor upgrading plan, as endorsed in 1991 by
Brookfield, New Milford, HVCEO and Conn DOT, calls for continuation
of a limited access Route 7 beyond its current terminus at
Route 202 in Brookfield, in the form of a four lane “Brookfield
Bypass.” This facility will then terminate at the existing
Route 7 just south of the New Milford Town Line.
From that
point northward, Route 7 will be rebuilt as a four lane roadway
to Route 67 at Veterans Bridge in central New Milford. The
design cross section will incorporate a median from the northern
end of the Brookfield Bypass northerly to the vicinity of
the new Still River Road in southern New Milford, just north
of Lanesville Road. Beyond that point to Veterans Bridge no
median will be utilized.

The
map above identified current travel time in ten minute intervals
from I-84
Exit 7 north towards New Milford. The ten minute line (brown)
is south
of the New Milford town boundary and the twenty minute line
(red)
is south of the New Milford Town Center.

In
contrast to the top map, this second map projects future travel
time in ten minute
intervals from I-84 Exit 7 north towards New Milford if the
entire Route 7 Expressway
had been built. The ten minute line (brown) reaches will into
New Milford and
the twenty minute line (red) well past New Milford Center.
The current plan,
a combination of Expressway extension and widening, will provide
much of this time savings benefit.
FUTURE
UPGRADING PLAN
On Brookfield's
portion of the completed Expressway is an overpass carrying
Route 133. HVCEO Bulletin 80, dated 12/1994 and addressing
Brookfield’s Federal Road traffic issues, reviewed the
concept of adding ramps from and to the Route 7 Expressway
to Route 133 at this location.
That study
indicated a proposed interchange could be oriented to and
from the south, essentially a half interchange, and would
reduce traffic on nearby Federal Road and its busy intersections.
The new new ramps would be a spur to economic development
and motorists using the ramps would reduce their travel
time.
The
Brookfield, CT Plan of Conservation and Development, dated
11/2001 specifically endorses construction of this interchange.
The Plan recommends that Conn DOT "construct a partial
interchange at Junction Road (Route 133) to relieve traffic
heading easterly, provide better access for the business zoned
land in this part of the corridor, and provide a convenient
access point for emergency vehicles."
Detailed feasibility of this Route 133 interchange concept
remains to be explored. However, this cannot occur until current
Route 7 improvements in the vicinity are completed, as traffic
projections based upon current volumes and turning movement
patterns would not be valid after those new facilities are
in operation.
Given the magnitude of the widening investment for the existing
right of way, stringent air quality laws, local opposition,
development in the path of possible rights of way and limited
federal funding, it seems very unlikely as of this Plan update
that the remainder of the old Route 7 Expressway extension
plan to central New Milford will ever be revived.
3C. ROUTE 25
IN NEWTOWN, CT
The relocation of Route 25 as an expressway on a new
alignment from I-95 in Bridgeport northerly through Newtown
to I-84 was a goal of Conn DOT for many decades. But this
is no longer being considered. A complete review of Route
25 issues is available from HVCEO.
3D. I-84 IN
DANBURY, BETHEL,
BROOKFIELD AND NEWTOWN, CT
OVERVIEW
Back in the 1950's, the major east-west flow of traffic through
the Housatonic Valley Region made use of two lane Route 6.
Route 6 passed westerly through Sandy Hook Center in Newtown,
then by the Flagpole, on to the Stony Hill section of Bethel,
thru Downtown Danbury, then along the Mill Plain section of
western Danbury, on into New York State.
As a bypass
for this corridor I-84 arrived from the east in 1958, crossing
the Housatonic River into the Region on the early fifties
era Rochambeau Bridge and ending temporarily at Route 34,
Exit 11, in Newtown.
Then on 12/16/1961 I-84 as the “Yankee Expressway”
(a name voted by the General Assembly in its 1961 session)
opened across the Region, passing through Newtown, Bethel,
the southernmost tip of Brookfield, and Danbury to link up
with New York State sections. Thus most thru traffic no longer
used Route 6.
The I-84
corridor within the Region extends from the Newtown-Southbury
Town Line on the east to the New York State-Danbury line on
the west, for a total length of approximately 18.5 miles.
Traffic volumes in early years, such as 1966, were a small
fraction of what they are today.
The introduction of this interstate route, coupled with construction
of I-684 nearby in New York State, has been a tremendous stimulus
to the Region's economic growth.

Within
the national interstate routing system I-84 is relatively
short, as its end points are in Scranton, Pennsylvania on
the west and in Sturbridge, Massachusetts on the east. I-684
joins it from the southwest a few miles west of Danbury in
New York State.
Oriented to nearby Westchester County and Manhattan, I-684
is also a stimulus for the Region's growth.
I-84 has
become the modern "Main Street" of the Housatonic
Valley Region, an indispensable economic asset, and of practical
importance to the citizens of all ten municipalities.
Fortunately, when I-84 was constructed in the early 1960's
the alignment was designed to high standards, with gentle
horizontal and vertical curves. The lanes were also given
ample width, with breakdown lanes along the right shoulder
in most locations. Sight distances were also adequate for
the most part.

Click
on the map to view a larger image.
However,
time has shown that the key weakness of the original design
was in the capacity given to exits. While not noticeable in
the early 1960's, exit capacity limitations present serious
drawbacks with today's traffic volumes. These problems include
left-hand entrances and exits, short weaving sections, inconsistent
exit patterns, and limited storage at ramps.
The public
should not feel that due to the massive scale of I-84 these
problems cannot be remedied. Some already have been. Fortunately,
the traffic capacity of I-84 is not be rigidly fixed and will
continue to evolve. The question is one of money for the necessary
upgrades.
Change
on I-84 is possible. Consider that I-84 in this Region has
undergone some significant capacity expansions since its completion
in 1962. The major ones are as follows:
1. The
original 1958 section in Newtown, built with only one lane
in each direction from the Rochambeau Bridge over the Housatonic
River at the Newtown-Southbury line westerly to Exit 11 in
Newtown, had its capacity expanded by 100% to four lanes in
1973.
Also at that time, Exit 11 was relocated three quarters of
a mile to the east with direct access to Route 34 removed.
There it was transformed into a high capacity free flow interchange
for a planned connection to a proposed Route 25 Expressway
running northward from Monroe and Bridgeport. That expressway
connection will now never be built.
For the
record, HVCEO never endorsed the concept of this proposed
Route 25 Expressway.
2. Then
in the late 1970's the I-84 Rochambeau Bridge itself from
Southbury to Newtown over the Housatonic River was paralleled
with a new and nearly identical bridge. The first bridge alone
had a cross section of four lanes; the new arrangement has
two lanes on each bridge and a potential for an additional
two lanes on each in reserve for the future.
3. In
the early 1980's a third westbound lane was added between
Exit 1 and Exit 3 in Danbury, and a third eastbound lane was
added in Danbury from Exit 2 to Exit 3. A new Exit 1 at a
new location, serving Saw Mill Road and Route 6 near the New
York line, was also added as part of this project.
What had been Exit 1 serving Old Ridgebury Road was rebuilt
and renamed Exit 2; then the original Exit 2 at West Kenosia
Avenue (consisting of a single eastbound exit ramp) was permanently
eliminated. This expansion served to facilitate the Carbide
office development on Danbury's west side, a statewide priority
at that time, and warmly embraced by the City of Danbury and
the Region.
4. In
1988 I-84 between Interchanges 4 and 7 was widened from four
to six lanes, a dramatic 50% increase in capacity in the highest
volume segment on I-84 in this Region. Back in the early 1960's
the I-84 cross section had been thoughtfully designed to permit
such a future capacity expansion by use of land in the median,
without the need to rebuild all bridges. This crucial project
derived from an HVCEO planning initiative.
As much
as these past investments are appreciated by the Region, insufficient
capacity for the long term on I-84 remains a key regional
concern. It is fortunately also a state concern, since I-84
is a gateway into Connecticut, and a federal concern as well
as a main gateway to New England.
Further
upgrading of I-84 in Danbury, Bethel, Brookfield and Newtown
is needed in order for it to continue to serve thru traffic
as well as be an effective "Main Street" for the
area. HVCEO's long range goal is to identify the issues involved,
qualify the Region for federal funds, and lobby to insure
I-84 improvements in a timely manner.
The adjacent region to the east, the Central Naugatuck Valley
Region, shares with us an intense interest in the future of
I-84. HVCEO and COGCNV
are committed to working together to improve I-84.
In the
late nineties HVCEO petitioned Conn DOT to undertake an in
depth analysis of I-84 upgrading needs. The response was very
cooperative and this effort was completed in 2000.
The results were then endorsed by HVCEO and made a part of
this Regional Transportation Plan. Some perspective is available
from the private Future
of I-84 in Danbury web site.
COST
OVERVIEW OF I-84
SAFETY AND CAPACITY NEEDS
The total cost by phase for all safety and capacity
needs is as follows:
PHASE
1:
$ 10,875,000 for 1-84 HIGHEST PRIORITY SMALL INTERCHANGE IMPROVEMENTS.
SEE DETAILS BELOW.
PHASE 2: $ 10,840,000 for 1-84
REMAINING SMALL SCALE INTERCHANGE IMPROVEMENTS.
PHASE 3: $ 83,180,000 for 1-84
MAJOR CAPACITY ADDITIONS AT INTERCHANGES. SEE DIAGRAMS FOR
EACH BELOW:
I-84
EXIT 2 LONG TERM IMPROVEMEN DIAGRAM
I-84
EXITS 3 AND 4 MEDIUM TERM IMPROVEMENT DIAGRAM
I-84
EXITS 3 AND 4 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXITS 5 AND 6 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXIT 7 MEDIUM TERM IMPROVEMENT DIAGRAM
I-84
EXIT 7 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXITS 8 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXITS 9 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXITS 10 LONG TERM IMPROVEMENT DIAGRAM
I-84
EXITS 11 LONG TERM IMPROVEMENT DIAGRAM
PHASE
4: $ 163,190,000
for 1-84 ADDITION OF THRU LANES TO THE MAIN LINE.
TOTAL:
$ 268,085,000
Phase
1 itself has sub-components and priorities. These details
are necessary here as coordinated lobbying will be most effective
if on a project by project basis:
PHASE
1: FIRST PRIORITY:
DANBURY EXIT 5: EXTEND WESTBOUND OFF RAMP, $1,000,000.
DANBURY EXIT 5: EXTEND EASTBOUND OFF RAMP, $1,500,000.
DANBURY EXIT 6: WIDEN WB OFF RAMP, WIDEN RT 37, ADD SIGNAL,
$300,000. FUNDED
DANBURY EXIT 6: EXTEND WESTBOUND OFF RAMP, $500,000. FUNDED
DANBURY EXIT 6: EXTEND EASTBOUND ON RAMP, $1,500,000. FUNDED
TOTAL: $4,800,000.
PHASE
1: SECOND PRIORITY:
DANBURY EXIT 8: EXTEND EASTBOUND ON RAMP, $230,000.
NEWTOWN EXIT 9: REDESIGN RAMP TERMINI AND SIGNALIZE EASTBOUND,
$100,000.
NEWTOWN EXIT 9: EXTEND WESTBOUND OFF RAMP $1,100,000.
NEWTOWN EXIT 9: EXTEND WESTBOUND ON RAMP, $1,000,000.
NEWTOWN EXIT 9: ADD EASTBOUND LEFT TURN LANE TO RTS 6 &
25 INT., $225,000.
NEWTOWN EXIT 11: LIGHTED SPEED SIGNS BEFORE WASSERMAN WAY,
$70,000.
NEWTOWN EXIT 11: NEW ON RAMP FROM TODDY HILL ROAD INT., $1,500,000.
(FOUND TO BE UNFEASIBLE).
TOTAL $4,225,000.
PHASE
1: THIRD PRIORITY:
DANBURY EXIT 2: EXTEND WESTBOUND ON RAMP, $500,000.
DANBURY EXIT 2: EASTBOUND SIGNAGE TO REST AREA AND LOCAL ROADS,
$100,000.
DANBURY EXIT 2: EXTEND EASTBOUND OFF RAMP, $500,000.
DANBURY EXIT 4: EXTEND EASTBOUND ON RAMP, $750,000.
TOTAL: $1,850,000.
The next step is for Conn DOT to undertake an environmental
assessment of I-84 from the New York State Line to Waterbury,
in conformance with FHWA guidelines, in order to qualify this
32 mile segment of roadway for major federal funding."
This should begin early in 2005.

ECONOMIC
IMPACT STATEMENT
I-84 improvement
advocates are asked to please spread
the ideas in this I-84 economic impact statement:
The
upgrading of the I-84 Corridor can yield handsome economic
benefits to the State of Connecticut, for this corridor is
a natural growth area for economic development in a global
market. This view was presented to the Greater Waterbury Chamber
of Commerce in September of 2003 by nationally known economic
growth expert Michael Gallis.
All
projections show that the New York Metro area will retain
a strong position in the new global economy. Connecticut can
benefit by positioning itself as a distinct submarket of that
area. While two thousand units of local government compete
for economic growth in just this one metro area, selling ourselves
as one of the “nine interstate spokes out of NYC”
puts us on the world radar screen.

An excerpt from the Gallis
report, which projects
a shift to growth to the Danbury-Waterbury I-84 corridor
A gigantic lattice of trade routes is growing just to the
west of the Washington to Boston coastal corridor. One million
square foot distribution centers appearing on I-81 are one
symptom of this. North and south NAFTA trade routes, such
as I-87 nearby, are also driving its formation.
The
Hudson River presents a barrier to global competitiveness
here to its east. But I-84 holds the high card of a free flowing
connection across that barrier. The position of I-84 through
western Connecticut serves the New England market, then also
the New York Metro, then triple duty as a bypass for congested
I-95 and NYC.
From the perspective of emerging globally influenced trade
patterns, this geography presents the Danbury to Waterbury
Corridor with great opportunity. (New and fast multi-lane
Route 7 connections north to New Milford are about to pull
it more into the I-84 orbit as well).
In reaction to these forces, to insure economic viability
for all of Connecticut, I-84 capacity upgrading must be a
high statewide priority.
|