Contents
---
1. Introduction --- 2.
Roadway System
3a. I- 84 ---
3b.
RT 7 South --- 3c.
RT 7 North
4. Projects by Municipality --- 5.
Bus Plan --- 6.
Rail Plan
Other Elements 7a, 7b,
7c, 7d,
7e
--- 8.
Resource Center
INTRODUCTION
This section provides a summary of the costs of projects recommended
in the Regional Transportation Plan. This is followed by an
estimate of the revenues that will be used to finance the
Plan’s recommended improvements. But
since this is a long range systems level plan, many of the
cost estimates and most of the revenue estimates are preliminary.
The intent is to prepare an approximate, but realistic estimate
of total program cost.

Federal rules require that fiscal priorities be
set.
HVCEO
is required by the rules of the federal transportation planning
process to include this financial component within its Regional
Transportation Plan to insure that the HVCEO Plan can be reasonably
implemented, since overall federal and state funding will
be limited.
In meeting
this requirement, it is HVCEO's intent that the program's
many planning bulletins and other data reports with their
cost estimates be considered as documentation that is in aggregate
much of the support for this financial component. Conn DOT
planning documents are also used for this purpose.
Importantly,
the federal process requires that the regional plan be "fiscally
constrained." That is, proposed projects within the plan
must be prioritized such that only those that are fundable
over the period 2007 - 2035 are included.
This setting
of priorities allows other processes such as air quality analysis
and capital programming to proceed on a realistic basis. As
required by federal rules, projects to be placed on the Region's
capital program of projects will be drawn from the lists of
needed transit and roadway projects in this Plan.
HVCEO
certifies that it will not attempt to program projects costing
more than the 28 year theoretical amounts set by Conn DOT
for "financial constraint" planning purposes. Projects
costing in excess of these Conn DOT determined amounts could
be considered to be scheduled for the "off years",
that is, beyond the scope of this current Plan.
1.
TRANSPORTATION SYSTEM IMPROVEMENTS 2007-2035
System improvement projects are those which enhance safety,
improve mobility, increase system productivity or promote
economic growth. The Conn DOT estimate as of 2/27/2006 of
funds to be available to the Housatonic Valley Region for
the 28 year planning period is $627,376,551.
This Plan's total is a lesser amount, $202,277,000, as defined
by municipality: Bethel $11,600,000; Bridgewater $2,000,000;
Brookfield $15,940,000; Danbury $86,793,000; New Fairfield
$2,050,000; New Milford $25,536,000; Newtown $43,900,000;
Redding $622,000; Ridgefield $2,000,000; Sherman $5,836,000;
Regional Enhancement $6,000,000; totaling to $202,277,000.
Thus the
HVCEO Region is not near financial constraint limits as of
this Plan update. The reason is that our most costly and largest
projects are fortunately removed by Conn DOT into the "Major
Projects of Statewide Significance" category (see Section
3 below).
Therefore
there is room to program some additional municipal improvement
projects, and federal fiscal constraint issues are not being
violated by this Plan.
Please note that the Region anticipates at a later date the
addition of significant additional capital costs to be documented
by a Danbury Branch Rail Line Passenger Improvement Plan.
This plan is being prepared by Conn DOT. No cost estimate
is yet available, and the Council has not yet officially endorsed
inclusion into this Regional Transportation Plan.

2.
TRANSPORTATION SYSTEM PRESERVATION 2007-2035
Preservation projects are such as state roadway repavings,
bridge repair or replacement, and other reconstruction in
place, as required under Conn DOT maintenance schedules. The
amount projected for the Housatonic Valley Region by the methodology
of the Conn DOT 2/27/2006 memo for a twenty eight year period
is $611,028,000.
Such projects
are not listed directly in the HVCEO Transportation Plan.
Rather, HVCEO will work cooperatively with Conn DOT during
the 28 year period to maximize the effectiveness of such expenditures
on the Region and not exceed its share, thus remaining fiscally
constrained.
It should be noted that as Connecticut places a high priority
on maintenance, the funds to pay for it have already been
identified in the State’s financial planning guidelines.
Accordingly, individual planning regions are not required
to identify funding sources for the costs of keeping state
roads in good repair.
3.
TRANSPORTATION SYSTEM MAJOR
PROJECTS OF STATEWIDE SIGNIFICANCE 2007-2035
Within the statewide umbrella of financial constraint, Conn
DOT has reserved certain additional theoretically available
funds for "Major Projects of Statewide Significance."
According
to the Conn DOT estimate of 2/27/2006, over the next twenty
eight yeas there will be $60,000,000 for Route 7 in Brookfield,
$268,000,000 for I-84 improvements in the Region, and $18,100,000
for Route 7 in Danbury and Ridgefield, for a total of $346,100,000
in "Major Projects of Statewide Significance " funding
support for these Housatonic Valley needs.
4.
TOTAL COST FOR CATEGORIES 1-3 ABOVE FOR 2007- 2035
The three figures above total to $1,159,405,000, which is
less than the allowed maximum of $1,584,404,617. Thus costs
are within this theoretical funding maximum.
As the
above HVCEO system improvement costs are below the ceiling
for that category, and "statewide" and "preservation"
categories are maximums already set by Conn DOT, this HVCEO
Plan conforms to the fiscal constraint rule.
1.
System Improvements: $202,277,000
2. System Preservation: $611,028,000
3. Statewide Significance: $346,000,000
Total
included (1-3 above) in this Plan: $1,159,305,000
Total still available to this Plan: $425,100,000
Combined "included" and "still available":
$1,584,405,000
Maximum
allowable: $1,584,405,000
Overall,
HVCEO will advance projects in accordance the theoretical
maximums and agrees to maintain a fiscally constrained plan.
5.
TRANSPORTATION SYSTEM TRANSIT 2007-2035
Included in this section are capital and operating costs for
Housatonic Area Regional Transit (HART) system services as
well as commuter rail services. A maximum amount projected
to be available by planning region has not been calculated
by Conn DOT.
Rather,
all transit capital spending for the Housatonic Region will
be based upon Conn DOT's latest Capital Project Management
Plan. This Conn DOT Plan consists of the projects and estimated
costs required to bring the existing public transit systems
to a state of good repair, to maintain them in that condition,
and to replace rolling stock as life cycles dictate. The cost
to operate rail and bus transit systems are additional.
In order
to meet the condition of financial constraint, HVCEO will
work within the confines of the Conn DOT Capital Project Management
Plan. HVCEO will request that priority projects be included
on that program.
Since
Conn DOT approval is mandatory for funding and state totals
are limited, and since the Capital Project Management Plan
is itself appropriately fiscally constrained, meeting the
financial constraint requirement for transit for the Region
is assured.
The current
Conn DOT Capital Project Management Plan can be accessed thru
Conn DOT.
For the
future, it is understood that once the rail passenger improvement
plan is completed, then Conn DOT and this planning process
will need to cooperatively identify new revenue sources before
the service can be implemented.
Transportation
Plan Sections 1 - 2
- 3
- 4
-
5 - 6-
7- 8
|